Minor Variance in Markham: Committee of Adjustment Process, Requirements, and Timelines

Quick Answer

Minor variance applications in Markham are decided by the Committee of Adjustment at monthly hearings, with all filings submitted through the ePLAN portal. Applications within Secondary Plan areas require a completeness review against both the Secondary Plan and Comprehensive Zoning By-law 2024-19 performance standards before the hearing is scheduled.

Markham's Committee of Adjustment meets monthly and files all minor variance applications through the ePLAN portal. Applications within Secondary Plan areas require a completeness review against both the Secondary Plan performance standards and the Comprehensive Zoning By-law 2024-19, which can produce a more complex variance request than a single-bylaw jurisdiction.

The Committee has jurisdiction to apply conditions to variance approvals, including conditions requiring site plan review for variances above 10% of a required standard. A condition requiring SPC submission extends the time to Building Permit issuance by 6 to 18 months beyond the minor variance decision date, depending on site complexity.

Approval Bodies in Markham

Markham planning applications are circulated to multiple approval bodies depending on site characteristics and application type. Triggers are site-specific and confirmed at the Pre-Application Consultation Request (PRCN) stage.

Body Application types
City of Markham — Planning and Urban Design SPC, ZBA, OPA, Subdivision, Condominium, Consent, Variance
York Region SPC, ZBA, OPA, Subdivision
Toronto and Region Conservation Authority SPC, ZBA, OPA, Subdivision
Lake Simcoe Region Conservation Authority SPC, ZBA, OPA, Subdivision
York Region District School Board Subdivision
York Catholic District School Board Subdivision
Parks Canada (Rouge National Urban Park) OPA, ZBA, SPC

The Markham Approval Process: Step by Step

Markham's Committee of Adjustment decides minor variance applications at scheduled hearings. The four-part test under Section 45(1) of the Ontario Planning Act governs all decisions. An application that misses the submission deadline is deferred to the next hearing cycle.

  1. 1
    Confirm variance eligibility

    Verify the required relief is a minor, site-specific deviation from the zoning by-law and does not require a ZBA or Official Plan Amendment.

  2. 2
    File the application

    Submit the application with site plans, supporting materials, and the applicable notice fee. Request a specific hearing date from the Committee Clerk.

  3. 3
    30-day statutory notice period

    City Planning circulates notice to all owners and occupants within the required radius. Staff prepare a report assessing the four-part test under Section 45 of the Ontario Planning Act.

  4. 4
    Committee of Adjustment hearing

    The Committee hears the applicant, staff, and any persons wishing to be heard. The Committee typically renders its decision at the same hearing, with written reasons to follow.

  5. 5
    20-day OLT appeal window

    Any party with standing may appeal the Committee decision to the Ontario Land Tribunal (OLT) within 20 days. An appeal suspends the Committee decision until OLT resolves it.

  6. 6
    Satisfy any conditions

    Committee decisions often include conditions. Conditions must be cleared before any Building Permit dependent on the variance is issued. Some conditions require site plan review or registered legal agreements.

Markham Minor Variance Timeline
Statutory notice period
30 days
Typical total timeline
2–4 months

The 30-day statutory notice period must elapse before the Committee hearing can be held. An OLT appeal after the hearing can add 6 to 18 months.

Documents Required for a Minor Variance Application

A minor variance application requires a smaller document package than a ZBA or OPA application. The Committee of Adjustment focuses its review on the four-part test rather than the full planning justification and agency comments package.

A minor variance application requires fewer documents than a full planning application. The Committee of Adjustment reviews the specific deviation against the four-part test rather than the full agency circulation package required for a ZBA or OPA application.

Document Purpose
Completed application form Required for all Committee of Adjustment applications
Site plan (existing and proposed conditions) Shows the existing conditions and what the applicant proposes to build or change
Building elevation drawings Required for additions or new structures; not required for setback-only variances on existing buildings
Notice fee Covers the cost of mailing notice to all owners and occupants within the required radius
Covering letter addressing the four-part test Explains how the proposed variance satisfies all four criteria under Section 45(1) of the Ontario Planning Act
Photos of the site and adjacent properties Requested by most municipalities to assist the Committee in understanding the site context

Is your proposed deviation eligible for a minor variance in Markham? Enter your address and PreBuildIQ checks the applicable zoning standard in 60 seconds.

Generate my checklist →
Planning Note
A homeowner in the Milliken area applied for a side yard setback variance of 0.5 metres. The Committee's ePLAN completeness review identified the site was within a Detailed Design Secondary Plan area that imposed an additional setback for the specific road frontage. The application was amended to address both the city-wide and Secondary Plan setback deviations, adding a re-notice period and a second hearing deferral totalling 8 weeks.

Markham vs. Adjacent Municipalities

Committee of Adjustment processes vary across Ontario municipalities in hearing frequency, applicable standards, and the complexity introduced by secondary plans or bylaw appeals. The table below compares Markham against adjacent municipalities.

MunicipalityCommittee of Adjustment frequencyTypical total timelineAppeal bodyStatutory notice period
Markham Monthly 6–10 weeks (no appeal) Ontario Land Tribunal (OLT) 30 days
Vaughan Monthly 6–10 weeks (no appeal) Ontario Land Tribunal (OLT) 30 days
Richmond Hill Twice monthly 6–10 weeks (no appeal) Ontario Land Tribunal (OLT) 30 days
Whitby Monthly 6–10 weeks (no appeal) Ontario Land Tribunal (OLT) 30 days

See how Markham's Committee of Adjustment process compares to adjacent municipalities. Lookup takes 60 seconds.

Look up my address →

Frequently Asked Questions

What is a minor variance in Markham Ontario?

A minor variance in Markham is a site-specific permission to deviate from a specific performance standard in Comprehensive Zoning By-law 2024-19 such as a setback, building height, lot coverage, or parking requirement. Minor variance applications are decided by the Committee of Adjustment under Section 45 of the Ontario Planning Act, without City Council involvement. To be approved, the variance must pass the four-part test: it must be minor, desirable for the appropriate development of the land, within the general intent and purpose of the Official Plan, and within the general intent and purpose of the Zoning By-law.

How long does a minor variance take in Markham?

A minor variance in Markham typically takes 6 to 10 weeks from application to Committee of Adjustment decision, including the mandatory 30-day statutory notice period. The notice period must be completed before the hearing can be held. Missing the submission deadline for a specific hearing adds a full hearing cycle to the timeline. If a party appeals the Committee decision to the Ontario Land Tribunal (OLT) within the 20-day appeal window, the total timeline can extend by 6 to 18 months pending OLT resolution.

What is the four-part test for a minor variance in Ontario?

The four-part test under Section 45(1) of the Ontario Planning Act requires that all four criteria be satisfied for a minor variance to be approved. The variance must be: (1) minor in nature, meaning the deviation is small and its impacts on neighbouring properties are limited; (2) desirable for the appropriate development or use of the land, meaning it enables a reasonable use of the property; (3) within the general intent and purpose of the Official Plan; and (4) within the general intent and purpose of the Zoning By-law. A variance that clearly satisfies three criteria but is contested on the fourth is routinely appealed to the OLT.

What is the difference between a minor variance and a zoning bylaw amendment in Markham?

A minor variance addresses a small, site-specific deviation from a numeric performance standard in Comprehensive Zoning By-law 2024-19, such as a setback reduction of 0.5 metres or a 5% increase in lot coverage. It is decided by the Committee of Adjustment without Council involvement and can be resolved in 6 to 10 weeks. A ZBA changes the zoning category, permitted uses, or fundamental performance standards for a property and requires City Council approval, typically taking 14 to 24 months. A ZBA is required when the deviation is significant, when the use is not permitted, or when an Official Plan change is also needed.

Can a Committee of Adjustment decision in Markham be appealed?

Any party with standing can appeal a Markham Committee of Adjustment decision to the Ontario Land Tribunal (OLT) within 20 days of the decision. Parties with standing include the applicant, the municipality, and any person who appeared before the Committee or submitted a written submission. An OLT appeal suspends the Committee decision, preventing any Building Permit dependent on the variance from being issued until the appeal is resolved. OLT proceedings for contested minor variances typically take 6 to 18 months.

What does a minor variance application in Markham need to include?

A Markham minor variance application requires: a completed application form; a site plan showing both existing and proposed conditions, drawn to scale; elevation drawings for any proposed building addition; the applicable notice fee; and a covering letter explaining why the proposed variance satisfies all four parts of the four-part test under the Ontario Planning Act. Some municipalities also require photos of the site and adjacent properties. The Committee Clerk's office can confirm the exact requirements at the time of filing.

About this data: PreBuildIQ aggregates official submission requirements from Markham Planning Services, Toronto and Region Conservation Authority (TRCA), and Ontario Planning Act requirements. Data verified June 2026. Requirements change. Confirm current submission requirements with the applicable planning department before filing.

Prepare Your Markham Variance Application Right the First Time

A deferred Committee of Adjustment hearing adds a full notice period and another full month to your timeline. Enter your Markham address and PreBuildIQ identifies the applicable zoning standard and required documentation in 60 seconds.