Site Plan Control in Toronto applies to all development with no minimum GFA threshold. The Ontario Planning Act sets a 60-day statutory review period from acceptance of a complete SPC application, but most applications require multiple review cycles and take 12 to 18 months to final approval. Toronto Green Standard (TGS) compliance is mandatory for all new development, with the applicable version locked at the SPC submission date.
Toronto eliminated the Site Plan Control GFA exemption in 2022. A 5-unit infill development now triggers the same SPC process as a 500-unit tower. The City accepts only complete SPC packages, and the 60-day statutory decision period under the Ontario Planning Act begins on acceptance of a complete application. Missing a single drawing from the required set returns the entire package, resets the clock, and adds weeks to the Building Permit timeline.
Toronto Green Standard (TGS) Tier 1 compliance is mandatory for all new development. The TGS version that applies to a project is determined by the SPC submission date, not the date construction starts. A project that sails through ZBA approval and then waits six months before SPC submission may find it needs to meet a newer TGS version with stricter energy performance requirements, requiring updated MEP design before the SPC application is accepted as complete.
Toronto planning applications are circulated to multiple approval bodies depending on site characteristics and application type. Triggers are site-specific and confirmed at the Pre-Application Consultation (PAC) stage.
| Body | Application types |
|---|---|
| City of Toronto — City Planning Division | SPC, ZBA, OPA, Subdivision, Condominium, Consent, Variance |
| Toronto and Region Conservation Authority | SPC, ZBA, OPA, Subdivision |
| Toronto Transit Commission | SPC, ZBA |
| Heritage Preservation Services | SPC, ZBA, OPA |
| Toronto Public Health | SPC, ZBA |
| Toronto Green Standard Review | SPC, ZBA, OPA |
| Engineering and Construction Services | SPC, Subdivision |
Toronto's Site Plan Control process follows ZBA or OPA approval for most developments. The pre-application consultation confirms SPC drawing requirements and agency circulation. The 60-day statutory clock starts on acceptance of a complete SPC application.
Confirm the SPC study scope, required drawings, and any agency circulation requirements specific to the site. Pre-Consultation is often required before SPC applications are accepted.
Site plan, grading plan, servicing plan, landscaping plan, and building elevation drawings to City specifications. Consult the Pre-Application Consultation (PAC) output for the exact drawing list.
Studies confirmed at the Pre-Application Consultation (PAC) stage: Urban Design Brief, stormwater management report, arborist report, and others based on site triggers. File conservation authority permit application simultaneously.
A complete SPC application triggers the 60-day statutory review period under the Ontario Planning Act. An incomplete application is returned and the clock does not start.
City reviews SPC drawings against zoning standards, Official Plan policies, and urban design guidelines. Agency comments are incorporated into the SPC completeness review.
City Planning provides consolidated comments. Revisions typically address servicing connections, grading, landscaping, and urban design adjustments.
The conservation authority permit must be confirmed before the Site Plan Agreement is executed. File the CA permit application at the same time as the SPC submission to avoid sequential delays.
Agreement is signed by the owner and the municipality. Building Permit application can proceed after execution. Some municipalities require the upper-tier regional authority to execute the agreement as well.
Statutory minimum under the Ontario Planning Act. Actual SPC timelines depend on drawing revision cycles, conservation authority permit requirements, and Site Plan Agreement negotiation.
Studies are confirmed at the Pre-Application Consultation (PAC) stage and vary by site characteristics, proposed use, and triggering conditions specific to the property. The tables below cover verified study requirements from PreBuildIQ's dataset for Toronto applications under Zoning By-law 569-2013.
| Study / Document | Application types |
|---|---|
| Boundary Plan of Survey | OPA, ZBA, Subdivision, Condominium, SPC, Consent to Sever |
| Concept Site and Landscape Plan | OPA, ZBA |
| Contaminated Site Assessment / Phase 1&2 ESA | OPA, ZBA, Consent, SPC, Minor Variance |
| Context Plan | OPA, ZBA, Subdivision, Condominium, SPC |
| Draft Official Plan Amendment | OPA |
| Draft Zoning By-law Amendment | ZBA |
| Floor Plans | ZBA, SPC, Consent to Sever |
| Geotechnical Study and Hydrological Review | ZBA, Subdivision, Consent to Sever, SPC |
| Heritage Impact Assessment | OPA, ZBA, Subdivision, SPC, ZBA already addressed heritage). May be required: Consent, Variance for Heritage Register properties; applications adjacent to Heritage Register properties; Heritage Permit applications. |
| Methane Gas Study | OPA, ZBA, Subdivision, SPC |
| Arborist Report | ZBA, Subdivision, Condominium, SPC, Consent, Variance |
| Conceptual Grading Plan | ZBA |
| 3D Building Mass Model | OPA, ZBA, SPC |
| Landscape and Planting Plan | SPC |
| Lighting Plan | SPC |
| Planning Rationale / Planning Justification Report | Full: OPA, ZBA, Subdivision, Condominium, significant SPC. Covering Letter: new condominiums, smaller SPC, Part Lot Control, Plan Revisions, Consent. |
| Project Data Sheet | OPA, ZBA, Subdivision, Condominium, SPC |
| Public Consultation Strategy Report | OPA, ZBA, Subdivision, Condominium |
| Roof Plan | ZBA, SPC, Consent to Sever |
| Servicing Report | OPA, ZBA, Subdivision, SPC |
| Simplified Report Graphics | OPA, ZBA |
| Site and Building Elevations | ZBA, SPC, Consent to Sever |
| Site and Building Sections | ZBA, SPC, Consent to Sever |
| Site Grading Plan | SPC |
| Site Plan | ZBA, SPC |
| Site Servicing Plan | SPC |
| Soil Volume Plan | ZBA, Subdivision, Consent to Sever, SPC |
| Stormwater Management Report | ZBA, Subdivision, SPC |
| Topographic Survey | OPA, ZBA, Subdivision, Condominium, SPC, Consent to Sever |
| Transportation Impact Study | OPA, ZBA, Subdivision, SPC, Consent to Sever, Variance |
| Tree Protection Plan | ZBA, Subdivision, SPC, Consent, Variance |
| Underground Garage Plans | ZBA, SPC |
| Study / Document | Triggered when |
|---|---|
| Community Services and Facilities Study | OPA, ZBA, Subdivision |
| Land Use Compatibility Study | OPA, ZBA, SPC |
| Conceptual Servicing Plan | OPA, ZBA |
| Construction Management Plan | TBD at pre-con |
| Cultural Heritage Evaluation Report | OPA, ZBA, Subdivision |
| Draft Plan of Condominium | Condominium |
| Draft Plan of Subdivision | Subdivision |
| EMF Management Plan | OPA, ZBA, Subdivision, SPC |
| Energy Modelling Report | SPC |
| Energy Strategy / Net Zero Strategy | OPA, ZBA, Subdivision |
| Environmental Impact Study | OPA, ZBA, Subdivision, SPC |
| Erosion and Sediment Control Plan | |
| Housing Issues Report | OPA, ZBA, Rental Housing Demolition & Conversion, Condominium |
| Perspective Drawing | SPC |
| Architectural Control Guidelines | Subdivision |
| Avenue Segment Review | OPA, ZBA |
| Block Context Plan | OPA, ZBA, Subdivision, SPC, Consent to Sever |
| Archaeological Assessment | OPA, ZBA, Subdivision, SPC, Consent, Minor Variance |
| Detailed Colour Elevations | SPC |
| Accessibility Checklist | TBD at pre-con |
| Aeronautical Report | OPA, ZBA, SPC |
| Air Quality and Odour Study | ZBA, Subdivision, SPC |
| Natural Heritage Impact Study | OPA, ZBA, Subdivision, Consent to Sever, SPC |
| Noise Impact Study | ZBA, SPC, Subdivision, Consent to Sever |
| Pedestrian Level Wind Study | ZBA |
| Public Utilities Plan | ZBA, SPC |
| Rail Safety and Risk Mitigation Report | ZBA, SPC, Subdivision |
| Subdivision Concept Plan | Subdivision |
| Sun/Shadow Study | ZBA, 20m); may also be required for <20m near shadow-sensitive areas |
| Toronto Green Standard Compliance | ZBA, SPC, Subdivision |
| Urban Design Guidelines | ZBA, Subdivision, SPC |
| Vibration Study | ZBA, SPC, Subdivision, Consent to Sever |
Which SPC studies and drawings does your Toronto site require? Enter your address and PreBuildIQ tells you in 60 seconds.
Generate my checklist →Site Plan Control requirements and timelines differ across Ontario municipalities based on the applicable conservation authority, whether delegated authority applies, and the presence of MTSA or Secondary Plan requirements. The table below compares Toronto against adjacent municipalities.
| Municipality | SPC statutory period | Typical SPC timeline | Pre-application term | Conservation authority |
|---|---|---|---|---|
| Toronto | 60 days | 9–18 months | Pre-Application Consultation (PAC) | TRCA |
| Mississauga | 60 days | 9–18 months | Pre-Application Consultation (PAC) | Credit Valley Conservation (CVC) |
| Vaughan | 60 days | 9–18 months | Pre-Application Consultation (PAC) | TRCA; dual bylaw compliance required during OLT appeal |
| Markham | 60 days | 9–18 months | Pre-Application Consultation Request (PRCN) via ePLAN | TRCA; York Region co-approves OPA |
See how Toronto's SPC process compares to adjacent municipalities. Address lookup takes 60 seconds.
Look up my address →Site Plan Control in Toronto requires submission of a complete set of SPC drawings including site plan, grading plan, servicing plan, landscaping plan, and building elevations to City specifications. Additional studies and documents confirmed at the Pre-Application Consultation (PAC) stage are also required at intake. The Toronto and Region Conservation Authority (TRCA) permit must be issued or confirmed as not required before the Site Plan Agreement can be executed. Building Permits cannot be applied for until the Site Plan Agreement is signed by all parties.
The Ontario Planning Act requires a decision within 60 days of acceptance of a complete SPC application. This statutory period applies to the City's decision only and does not include the conservation authority permit process, which runs in parallel. Most Toronto SPC applications take 9 to 18 months from submission to Site Plan Agreement execution, with larger or more complex applications taking up to 24 months. The 60-day statutory clock creates an obligation on the City, not a guarantee of resolution.
Site Plan Control in Toronto governs the relationship between a proposed development and its surrounding context: grading, servicing connections, landscaping, site access, and architectural interface with adjacent streets and properties. It requires a Site Plan Agreement between the developer and the municipality. A Building Permit governs the structural, fire, and life-safety compliance of the building itself under the Ontario Building Code. Building Permit issuance requires a valid Site Plan Agreement for any development subject to SPC.
Site plan approval studies in Toronto are confirmed at the Pre-Application Consultation (PAC) stage and vary by site characteristics. Commonly required: Stormwater Management Report, Urban Design Brief (for larger developments), Arborist Report (for sites with regulated trees), Functional Servicing Plan, and accessibility compliance review. For sites near Toronto and Region Conservation Authority (TRCA) regulated areas, a natural heritage assessment or environmental impact study may also be required. The Pre-Application Consultation (PAC) meeting is the definitive source for the specific study list for a given site.
Site Plan Control decisions in Toronto can be appealed to the Ontario Land Tribunal (OLT) within 20 days of the decision. SPC appeals are less common than ZBA or OPA appeals, but can arise when the City's conditions on the SPC are disputed by the applicant or when a third party objects to the design approval. An OLT appeal suspends the SPC decision, preventing Site Plan Agreement execution and Building Permit issuance until the appeal is resolved.
Site Plan Control in Toronto applies to most commercial, industrial, institutional, and multi-residential development as defined by the Ontario Planning Act and the municipality's Site Plan Control By-law. Single detached homes and duplex dwellings are typically exempt. Changes of use, expansions to existing commercial or industrial buildings above a certain threshold, and all new multi-unit residential development typically require SPC approval. The Pre-Application Consultation (PAC) stage confirms whether SPC applies to a specific site and what the applicable requirements are.
A missing drawing at SPC intake delays the Building Permit, which delays construction start. Enter your Toronto address and PreBuildIQ generates your complete SPC drawing and study list in 60 seconds.
Generate my checklist